The project manager called me this afternoon to give me an overall progress update. In addition to what I noted above several other things have been completed as well. The big thing inside is that drywall has been hung. And just this afternoon the water, sewer, and gas lines were finished, inspected, approved, and buried. He also told me that the sidewalk had been pulled up and re-poured because he wasn't pleased with the finish on the original one. I've arranged to meet him Monday afternoon to do another walkthrough to see the progress on the inside and take pictures.
Chronicling the process of building a Sienna model house with Ryan Homes and living in it.
Friday, March 21, 2014
Week 6 Progress
The house is coming right along. From the outside at least the major things completed this week have been the siding, shutters, trim, and garage door.
Saturday, March 15, 2014
Water and Sewer Lines
Jenny and I drove by the house this afternoon on the way out to get some groceries. We noticed as we approached that a small excavator was out front and a guy was working in one of the trenches that had been dug. I thought one of them was for the drain line from the French drain under the house but come to find out from talking to the contractor doing the work that it was our sewage line out front and water line on the side. Standing at the street I snapped a few photos:
Sewage line coming from the house.
Curving around to where it connects with the sewer underneath where the driveway will eventually sit.
Trench for the water line.
I didn't notice it until this evening until Jenny pointed it out but you can also see from that first photo above that the sidewalk that was poured earlier in the week has apparently been removed. It looked fine when I walked through with the project manager yesterday but something must have happened to cause it to be ripped up. I guess I'll ask him the next time he calls.
Friday, March 14, 2014
Insulation
The project managed called me yesterday and asked if I wanted to do another walkthrough with him now that insulation has been put up. I'm definitely not going to pass up an opportunity to go through there with him so we arranged to meet this afternoon. Seeing as I just went through there with him on Monday and the only thing that had been done so far as the insulation it didn't take very long as there wasn't much else to see. We talked briefly about the failed inspections from earlier in the week. He showed me where the missing fireblocking is supposed to go and also in the garage where the steel i-beam needs additional bolts. It didn't sound too major but at least the issues were caught and corrected.
As I left crews were working outside putting up the vinyl siding. I also noticed that the concrete for the sidewalk and front porch floor had been poured as well.
Sidewalk
Front porch.
Insulation along the side wall of the garage. They only add insulation to the living area walls of the house and don't do the parts of the walls of the garage that don't back up to inside areas of the house. I wish it had been an option to do the other areas as well. I insulated the walls of the detached garage on my current house and it made a big difference. I will probably eventually go back and do something similar in here as well depending on how cold it gets in the winter. I want to be able to work out there comfortably year round.
Insulated walls of the garage against the living areas of the house.
Uninsulated side wall.
Labels:
construction,
insulation,
Ryan Homes,
siding,
walkthrough
Wednesday, March 12, 2014
Failed Inspection
Throughout the build process Jenny and I have been checking the county inspection records that are available online. Everything so far has passed until today. Checking on it this afternoon the house has failed not one but two inspections.
Jenny and I both think based on the comment on the second framing inspection that the inspector is just a wee bit annoyed right now. I was supposed to meet up with the project manager this week to do another walkthrough once the insulation was up but it doesn't look like that will be happening until next week now. I drove by the house today and boxes of vinyl siding were sitting in the driveway so it looks like that will be done in the next few days at least.