Showing posts with label project manager. Show all posts
Showing posts with label project manager. Show all posts

Wednesday, June 25, 2014

Odds and Ends

A few various things from the past week or so:

-I discovered a downside to living in a new neighborhood weekend before last - I picked up a sheet metal screw in the tire of my car. I can't say for certain it occurred around our house but odds are it probably did. Thankfully it was only took a $10 plug to fix. (I really didn't relish the idea of replacing a less than two year old tire which is initially what it was looking like.)

-The door-to-door marketers have been really obnoxious since we moved in. At our old house we might get one once a month at most. Here it's been more like once or twice a week. I guess they see far more opportunity with new neighborhoods. It got bad enough that Jenny finally made a no solicitation sign for our front door.

-Speaking of things my wife has made she also did this wreath for our front door too:

-Aside from the various scuffs and smudges we put on the walls moving in we finally incurred the first self inflicted damage on the house a few weeks back. We had family over for our younger son's first birthday and because our cocker spaniel lacks any sort of manners we put in the master bedroom for the duration. He wasn't very happy about that to say the least so along with barking he also ripped up the carpet in front of the door.

-The project manager came out last Wednesday along with two other guys to fix the handful of issues we've had in the house since moving in. The soft spot in the floor upstairs ended up being a spot in the subfloor that just needed to be filled in with putty to level it out. The crack in the toilet tank in the hallway bath was limited to just the outside but the project manager went ahead and replaced it. (Learned something new - the bowl and tank are two separate pieces.) And the issue with the weather seal around the door was resolved by adjusting the strike plate. (I didn't know this was possible.) All told it took about an hour.

-There's one other small annoyance we have right now but there's nothing that can really be done about it until construction is finished concerns the sewer drain in front of our house. It currently has a barrier in front of it of rocks and wire to keep construction debris from flowing into it. Because of that however whenever we get anything short of a drizzle in a short period of time it backs up in the gutter and in front of our driveway. A few weeks ago we had a huge downpour that was high enough to keep us from going anywhere until it subsided. This was the scene a few weeks back during a particularly heavy spring storm:



Having been through several tropical storms in the past few years I'm a little concerned about what will happen if we get even more water within the span of a few hours or day as typically is the case with those.

Friday, April 4, 2014

Drywall and Primer

I've been a little behind on updates on here. The day after my last post on Week 6 progress we had the dreaded stomach virus make it's miserable way through our house starting with our youngest son. It delayed the drywall walkthrough as the day I was originally supposed to meet with the project manager I was feeling half dead and had to postpone it with him a few days.

When I finally met with last week not only was the drywall up but the first coat of primer had been put on the walls as well. He explained to me that painting is a multistep process done over the course of a week or so with primer, patching, paint, more patching, and another layer of paint added before it's finished. The kitchen and bathroom cabinetry had also been added with everything covered in plastic to keep it protected from stray paint.

On the outside the driveway was in the final stages of paving when I arrived for the walkthrough. Gutters had also been installed. With a lack of trees in our yard leaves won't be much of an issue but at some point I plan to get some sort of cover installed on those. Getting up on a ladder to clean the gutters on my existing one story house has been difficult enough and I definitely won't be climbing high enough to reach the second story on this one.

The project manager asked me not to include a picture of it but he was also going to be tearing up the sidewalk and getting it re-poured for the third time. I mention this because I've really appreciated his attention to detail and it seems like everything Jenny and I have noted as potential issues during construction he's already seen and made note of. The previous two pours of the sidewalk looked fine to us and we never would have thought to ask about it. But clearly he saw a problem both times warranting redoing it. I've also really appreciated his constant communication throughout the build. He's called at least once if not twice a week and always been willing to meet me for a walkthrough. As I've noted before Jenny and I have read through numerous other Ryan Homes building blogs and at least some of them have noted a lack of communication from the project manager but this has certainly not been an issue for us. 

On to photos:

Paved driveway.

Rear of house. Note the safety railing covering the sliding door. After we move in my brother-in-law is going to add a simple set of steps for us until we can build a deck. We opted not to one built during initial construction as our sales rep told us that their cost was around twice as much as what we could have it added for later. We're also probably going to add a patio of some sort too.

Monday, March 10, 2014

Pre-Drywall Meeting and Closing Scheduled

I met this afternoon with the project manager to do the pre-drywall walkthrough of the house. Similar to the walkthrough we did last Wednesday it was another chance to see everything done so far and prior to the hanging of drywall and ask questions. Similar to the pre-construction meeting Jenny and I read through numerous other Ryan Homes blogs to find out what to expect and questions to ask.

The major things were to double check to make sure that things such as cable and phone jacks, ceiling fan rough-ins, and similar things were installed and placed where we wanted them. Most everything else were things we went over in the walkthrough last week or even in the pre-construction meeting or subsequent phone calls with the project manager.

One thing I noticed today that I was especially impressed by was how thorough they seem to be with the energy efficiency thing. Everywhere you look there's either yellow or pink expanding insulation foam that has been used to seal every possible area where air could leak into the house. Even the electrical outlets and ceiling fan rough-ins have been sealed in this way.

Based on suggestions I received from several coworkers one thing I did today during the walkthrough was take photos of each wall to have a record of where the wires and plumbing are before they're covered up by drywall. This way if we ever want to hang a picture or something else that requires putting a nail into the wall we have a rough idea of where things are. (Along with using a stud/wire finder of course.)

Over the weekend we also received a letter in the mail with the schedule for our new home orientation meeting and closing. The former is scheduled for Tuesday April 22 and the latter for April 24. It sounds like this is pretty much set in stone at this point although after talking with my realtor the closing date might change slightly since we're using an outside law firm for settlement.

Breaker box in the garage.

Main air intake and wastewater lines.


Laundry room hook ups and plumbing for washing machine and dryer.

Upstairs central ductwork.

Upstairs bathroom plumbing.

Bedroom wiring.


Friday, February 28, 2014

Week 3 Progress

One thing I've noticed both in our neighborhood and on the various Building with Ryan blogs is that the framing of the house doesn't take very long at all. Ryan seems to have the process down to a science almost and doesn't waste time putting it together. Our house has certainly been no exception. Every day I stopped by this week there was progress.

When I stopped by Monday the crew had begun building the second floor:

When I went by Tuesday the garage floor had been poured and roof trusses had been delivered:



By Wednesday the rest of the second floor above the garage had been added along with the stairs:



On Thursday afternoon the roof was on and windows had been installed:

This afternoon I got a call from the project manager letting me know framing had been completed and roofing work would proceed this weekend. Next week work will commence on installing ductwork, wiring, and plumbing with the expectation that we will have a our pre-drywall walkthrough sometime in the next ten days. 

I had a chance to walk through it this evening. It's amazing to me how far things have progressed. Just three weeks ago the lot was still bare and now we've got a framed house.